Clirik, one of the best professional Raymond mill manufacturers in China, tell s you how to install Raymond roller mill correctly, with considerable service and satisfied Raymond mill price.
1.Firstly, put the base of arranger into pit and fill the pit. Pay attention to control a certain height, and then use level to adjust the upper plane "A", at the same time install drive device in the "A" surface and bolt it.
2.The main unit installation of Raymond mill. Before installation, rubber shockproof pad shoulb be filled on the base bottom plane contact with cement foundation and anchor bolt connection. and then use frame level to revise base "B" plane.The calibration points are the four cross reticule. At the same time adjust the two half coupling "C", "D", whose axis degree should be less than 0.20 mm. E1, E2 nonparallelism degree shall not be greater than 0.1 mm, the gap between "E1", "E2" should be kept within 5-8 mm.
3. The location of the pipework shall be installed according to the general layout and height, shall not be any change and h
eightening. Each pipe joint shall be sealed and tighten, make sure that have no leakage phenomenon. Electrical equipment should be accurate and reliable, all parts should be carried out commissioning after the installation.